Dear Sir / Madam, Recently TenneT has tendered the procurement of electricity to cover the electricity that is needed for the commissioning phase of the Cobra-cable. The commissioning phase covers 28 testing days, as from week 2019-27. The electricity for part of the tests, will be procured from a contracted supplier / BRP, where TenneT can order a profiled amount of electricity for one or more 15-minute-periods. This can be a supply to TenneT (for the purpose of a flow from the Netherlands to Denmark West) or consumption from TenneT (for the purpose of a flow from Denmark West to the Netherlands). Updated details of these orders can be found on the website of TenneT as one of the downloads at the following webpage: https://www.tennet.eu/our-grid/international-connections/cobracable/ . |
Regards,
TenneT TSO B.V.