Dear sir / madam,
For the timeframe(s) mentioned below TenneT requests market parties for extra reserve-capacity with activation time greater than or equal to 5 PTE (block-bids; pay as bid) to solve expected congestion in the area mentioned below, Reserve capacity in Both upward and downward direction area required; please respect the defined power categories.
If necessary after gate closure, you can ask TenneT to supply a request number (phone number is mentioned above).
Date: 26-jul-2019
Period
PTE: 57 t/m 72
Time: 15:00 - 18:00 h
Area: Nederland
Desired direction bid: upward / opregelend
Amount extra reserve-capacity: 300 MW
Regards,
TenneT TSO B.V.