Dear sir / madam,
For the timeframe(s) mentioned below TenneT requests market parties for extra reserve-capacity with activation time greater than or equal to 5 PTE (block-bids; pay as bid) to solve expected congestion in the area mentioned below, Reserve capacity in Both upward and downward direction area required; please respect the defined power categories.
If necessary after gate closure, you can ask TenneT to supply a request number (phone number is mentioned above).
Date: 26-jul-2019
Period 1
PTE: 57 t/m 60
Time: 14:00 - 15:00 h
Area: Eemshaven
Desired direction bid: downward / afregelend
Amount extra reserve-capacity: 104 MW
Period 2
PTE: 61 t/m 64
Time: 15:00 - 16:00 h
Area: Eemshaven
Desired direction bid: downward / afregelend
Amount extra reserve-capacity: 531 MW
Period 3
PTE: 65 t/m 68
Time: 16:00 - 17:00 h
Area: Eemshaven
Desired direction bid: downward / afregelend
Amount extra reserve-capacity: 643 MW
Period 4
PTE : 69 t/m 72
Time: 17:00 - 18:00 h
Area: Eemshaven
Desired direction bid: downward / afregelend
Amount extra reserve-capacity: 363 MW
Regards,