Dear sir / madam,
The transport capacity of the NorNed link is reduced because of maintenance.
Start date | 12-jun-2019 |
Start time | 06:00 |
Expected end date | 13-jun-2019 |
Expected end time | 01:00 |
Available transportcapacity NO->NL | 500 MW instead of 700 MW |
Available transportcapacity NL->NO | 500 MW instead of 700 MW |
Remark: The reduction does not affect the previously allocated transport capacity on the NorNed link.
Additional remarks
Reduction of the capacity of the Norned cable due to maintenance in Norway: 420 kV Saurdal-Ertsmyra, 420 kV Kvilldal-Holen and 420 kV Kvilldal-Saurdal.
Regards,
TenneT TSO B.V.