The reduced transport capacity and/or the expected end time of the reduction of the NorNed link has been changed.
Start date | 11-feb-2019 |
Start time | 06:00 |
Expected end date | 11-mrt-2019 |
Expected end time | 16:00 |
Available transportcapacity NO->NL | 700 MW |
Available transportcapacity NL->NO | 700 MW |
Remark: The reduction does not affect the previously allocated transport capacity on the NorNed link.
Additional remarks
Planned maintenance in Norway has been cancelled. There is still maintenance on 27-02-2019 and 28-02-2019. See publication on 17-12-2018.