Dear sir / madam,
For the timeframe(s) mentioned below TenneT requests market parties for extra reserve-capacity with activation time greater than or equal to 5 PTE (block-bids; pay as bid) to solve expected congestion in the area mentioned below, Reserve capacity in Both upward and downward direction area required; please respect the defined power categories.
If necessary after gate closure, you can ask TenneT to supply a request number (phone number is mentioned above).
Date: 26-dec-2018
Period 1
PTE: 25-28
Time: 06:00 - 07:00 h
Area: Hemweg
Desired direction bid: downward / afregelend
Amount extra reserve-capacity: 69 MW
Period 2
PTE: 29-32
Time: 07:00 - 08:00 h
Area: Hemweg
Desired direction bid: downward / afregelend
Amount extra reserve-capacity: 46 MW
Period 3
PTE: 33-36
Time: 08:00 - 09:00 h
Area: Hemweg
Desired direction bid: downward / afregelend
Amount extra reserve-capacity: 21 MW
Period 4
PTE : 37-40
Time: 09:00 - 10:00 h
Area: Hemweg
Desired direction bid: downward / afregelend
Amount extra reserve-capacity: 9 MW
Regards,