Responsible and innovative underground cable installation
01-05-2009
There is widespread public support for underground installation of new high-voltage lines. On account of system risks, TenneT has nevertheless decided in principle to construct new high-capacity transmission lines (with a voltage level of 380 kV) above ground for the time being. This decision is based on technical arguments related to grid operation, including the fact that underground cables have a negative impact on grid safety, and increase outage risks. This position paper explains these matters.
Downloads
Responsible and innovative underground cable installation (pdf 43,37 Kb)