Geachte heer / mevrouw,
De transport capaciteit van de NorNed kabel is beperkt wegens werkzaamheden.
Startdatum | 01-dec-2014 |
Starttijd | 00:00 |
Verwachte einddatum | 24-june-2019 |
Verwachte eindtijd | 24:00 |
Beschikbare transportcapaciteit NO->NL | 300 - 700 MW ipv 700 MW |
Beschikbare transportcapaciteit NL->NO | 700 MW ipv 700 MW |
Opmerking: De beperking heeft geen invloed op de reeds vrijgegeven transportcapaciteit van de NorNed kabel.
Overige opmerkingen
UPDATE: Due to a prolonged process in acquiring necessary permits, there will be a delay in the construction work in NO2 that will facilitate an ease in capacity restrictions from NO2 to DK1/NL upon completion. Until the grid capacity in the western part of Southern Norway is increased, congestions are expected in NO2. The total aggregated export capacity on HVDC connections from NO2 is up to 2232 MW, but may be reduced up to 400 MW due to load flow conditions. Hence the export capacity NO2-NL will vary in the range of 300-700 MW, and NO2-DK1 will vary in the range 1132-1532 MW. Capacity reductions on the HVDC connections will be done according to descriptions in the document "PRINCIPLES FOR DETERMINING THE TRANSFER CAPACITIES IN THE NORDIC POWER MARKET" chapter 5.2.1. For additional information, please also read Exchange information No. 30/2013 "Future NTCs on the NorNed and the Skagerrak interconnectors". Duration uncertainty is more than 31 days.
Hoogachtend,
TenneT TSO B.V.